Takt time

Major Topic Area: Lean, TOC concepts

What pace does your factory need to operate at in order to satisfy your customer? The answer to this question is your takt time.

Sample Calculation:

Total customer monthly demands are 10,000. Let's assume that there are 20 working days in a month and the plant only operates 8 hours/day. The total time available in the plant during the month is:

 20 x 8 x 60 x 60 = 576,000 seconds

Therefore, the plant has 576,000/10,000 = 57.6 seconds to produce one unit of production.

If a machine or operation in the plant cannot achieve the takt time rate is must be considered to be a constraint.

 

 

 